CLIFF AVENUE over BEN GARNETT WAY
0.48 S OF I-90 · County 063, Washington · Built 1969 · 2 Lanes · 710 vehicles/day
Overall
Deck
8
Very Good
Superstructure
8
Very Good
Substructure
8
Very Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 8 | Very Good |
| Superstructure | 8 | Very Good |
| Substructure | 8 | Very Good |
Location
47.646128, -117.416397
This bridge is in worse condition than 5.2% of bridges in County 063. The average bridge in Washington is 0 years old; this one is 57 years old.
Nearby Bridges
9TH AVENUE over BEN GARNETT WAY
Built 1963
I-90 over VIADUCT STA 1396 US 2
Built 1967
I-90 S-E RAMP over DIVISION ST
Built 1967
I-90 S-W RAMP over MCCLELLAN ST BERNARD ST
Built 1967
I-90 E-N RAMP over BROWNE ST
Built 1967
I-90 W-N RAMP over HOWARD ST
Built 1967
W-CEDAR RAMP over CITY STREET (JEFFERSON)
Built 1967
SHERMAN ST over I-90
Built 1970
JEFFERSON-W RAMP over PARKING LOT
Built 1967
WALNUT-E RAMP over PARKING AREA
Built 1967
Bridge Details
- Structure #
- 085322000000000
- Year Built
- 1969
- Length
- 36.3 m (119.1 ft)
- Max Span
- 36.3 m
- Width
- 12.2 m (40 ft)
- Lanes
- 2
- Daily Traffic
- 710
- Material
- Prestressed Concrete Continuous
- Design
- Box Beam or Girders - Multiple
- Owner
- City or Municipal Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $904,000
- Total Project Cost
- $1,809,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.