KRAMER PARKWAY over I-90

5.7 E JCT SR 27 · County 063, Washington · Built 2023 · 2 Lanes · 1,717 vehicles/day

Overall
Good
Deck
8
Very Good
Superstructure
8
Very Good
Substructure
8
Very Good

Condition Ratings

ComponentRatingDescription
Deck 8 Very Good
Superstructure 8 Very Good
Substructure 8 Very Good

Location

47.667389, -117.122064

This bridge is in worse condition than 5.2% of bridges in County 063. The average bridge in Washington is 0 years old; this one is 3 years old.

Nearby Bridges

Bridge Details

Structure #
0019692A0000000
Year Built
2023
Length
77.5 m (254.3 ft)
Max Span
27.3 m
Width
17.3 m (56.8 ft)
Lanes
2
Daily Traffic
1,717
Material
Prestressed Concrete Continuous
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$2,356,000
Total Project Cost
$4,713,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.