PR 2 189.6 KM over CRISTAL CREEK

6 KM NORTHWEST OF GUANICA · County 055, Puerto Rico · Built 1979 · 4 Lanes · 24,400 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Poor
Culvert
4
Poor

Bridge Details

Structure #
016651
Year Built
1979
Length
8.2 m (26.9 ft)
Max Span
4 m
Width
40.9 m (134.2 ft)
Lanes
4
Daily Traffic
24,400
Material
Concrete Continuous
Design
Culvert
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$0
Total Project Cost
$70,000