PROJECT AND PUBLIC over THE DALLES DAM
SOUTH ACCESS BR OVER UPRR · County 065, Oregon · Built 1954 · 2 Lanes · 200 vehicles/day
Overall
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 6 | Satisfactory |
| Superstructure | 6 | Satisfactory |
| Substructure | 7 | Good |
Location
45.620889, -121.112583
This bridge is in worse condition than 27.7% of bridges in County 065. The average bridge in Oregon is 0 years old; this one is 72 years old.
Nearby Bridges
I-84 (HWY 002) over THE DALLES DAM ACC
Built 1954
I-84 (HWY 002) over FIFTEEN MILE CREEK
Built 2010
VIEWPOINT ROAD over FIFTEEN MILE CREEK
Built 1919
I-84 (HWY 002) WB over UPRR
Built 1965
I-84 (HWY 002) over UPRR
Built 1964
PROJECT AND PUBLIC over THE DALLES DAM
Built 1956
US 197 (HWY 004) over COLUMBIA RIVER
Built 1954
US 197 over COLUMBIA R SP & S RY
Built 1954
LOWER EIGHTMILE RD over EIGHTMILE CREEK
Built 2001
FIFTEEN MILE ROAD over FIFTEENMILE CR
Built 1965
Bridge Details
- Structure #
- CEPNPPOR000TD08
- Year Built
- 1954
- Length
- 29.3 m (96.1 ft)
- Max Span
- 20.7 m
- Width
- 10.8 m (35.4 ft)
- Lanes
- 2
- Daily Traffic
- 200
- Material
- Concrete
- Design
- Stringer/Multi-beam or Girder
- Owner
- Corps of Engineers (Civil)
- Last Inspected
- N/A
- Est. Improvement
- $305,000
- Total Project Cost
- $458,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.