US 197 (HWY 004) over COLUMBIA RIVER
EAST END OF THE DALLES · County 065, Oregon · Built 1954 · 2 Lanes · 6,795 vehicles/day
Overall
Deck
7
Good
Superstructure
6
Satisfactory
Substructure
6
Satisfactory
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 7 | Good |
| Superstructure | 6 | Satisfactory |
| Substructure | 6 | Satisfactory |
Location
45.610469, -121.139503
This bridge is in worse condition than 27.7% of bridges in County 065. The average bridge in Oregon is 0 years old; this one is 72 years old.
Nearby Bridges
US 197 over COLUMBIA R SP & S RY
Built 1954
PROJECT AND PUBLIC over THE DALLES DAM
Built 1956
I-84 (HWY 002) over UPRR
Built 1964
I-84 (HWY 002) over THREE MILE CREEK
Built 2016
US 197 (HWY 004) over UPRR & FRONTAGE RD
Built 1954
US 197 (HWY 004) over HWY 002
Built 1964
HWY 292 over THREE MILE CREEK
Built 2003
I-84 (HWY 002) over FIFTEEN MILE CREEK
Built 2010
VIEWPOINT ROAD over FIFTEEN MILE CREEK
Built 1919
PROJECT AND PUBLIC over THE DALLES DAM
Built 1954
Bridge Details
- Structure #
- 06635Q004 00000
- Year Built
- 1954
- Length
- 1019.6 m (3345.1 ft)
- Max Span
- 175.6 m
- Width
- 9.9 m (32.5 ft)
- Lanes
- 2
- Daily Traffic
- 6,795
- Material
- Steel Continuous
- Design
- Truss - Thru
- Owner
- State Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $10,711,000
- Total Project Cost
- $17,138,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.