MCCULLEY ROAD over JIRRIGATION CANAL
0085 MI S OF HWY 50 · County 035, Oregon · Built 1979 · 2 Lanes · 164 vehicles/day
Overall
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 7 | Good |
| Superstructure | 7 | Good |
| Substructure | 7 | Good |
Location
42.000797, -121.427964
This bridge is in worse condition than 9.3% of bridges in County 035. The average bridge in Oregon is 0 years old; this one is 47 years old.
Nearby Bridges
STATE LINE RD over IRRIGATION CANAL
Built 1969
STATE LINE RD over DRAINAGE DITCH
Built 1971
HARPOLD ROAD over J IRRIGATION CANAL
Built 1979
COUNTY ROAD 112 over J CANAL
Built 1940
6th Street over D CANAL
Built 2000
DRAZIL RD over D IRRIGATION CANAL
Built 1979
SUTY ROAD over IRRIGATION CANAL
Built 1974
HARPOLD RD over IRRIGATION CANAL
Built 1960
OR 39 (HWY 050) over USRS CANAL
Built 1962
GAINES ROAD over J IRRIGATION CANAL
Built 1979
Bridge Details
- Structure #
- 35C152117300085
- Year Built
- 1979
- Length
- 13.1 m (43 ft)
- Max Span
- 12.5 m
- Width
- 9.8 m (32.2 ft)
- Lanes
- 2
- Daily Traffic
- 164
- Material
- Prestressed Concrete
- Design
- Slab
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- N/A
- Total Project Cost
- $0
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.