J CONNOR ROAD over PISCATAQUOG RIVER
0.18 MI FROM NH RTE 114 · County 011, New Hampshire · Built 2003 · 2 Lanes · 96 vehicles/day
Overall
Deck
8
Very Good
Superstructure
8
Very Good
Substructure
6
Satisfactory
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 8 | Very Good |
| Superstructure | 8 | Very Good |
| Substructure | 6 | Satisfactory |
Location
43.111089, -71.755456
This bridge is in worse condition than 60.8% of bridges in County 011. The average bridge in New Hampshire is 0 years old; this one is 23 years old.
Nearby Bridges
NH 77 NH114 over PISCATAQUOG RIVER
Built 1939
RESERVOIR DRIVE over PISCATAQUOG RIVER
Built 1993
WOODBURY ROAD over PISCATAQUOG RIVER
Built 1940
RESERVOIR DRIVE over PISCATAQUOG RIVER
Built 1994
NH 77 TRUCK ROUTE over PISCATAQUOG RIVER
Built 1940
RIVER ROAD over PISCATAQUOG RIVER
Built 1940
PEASLEE ROAD over PISCATAQUOG RIVER
Built 2015
ABIJAH BRIDGE ROAD over LAKE HORACE
Built 2009
ABIJAH BRIDGE ROAD over DUDLEY BROOK
Built 1999
NH149 over PISCATAQUOG RIVER
Built 1939
Bridge Details
- Structure #
- 026700790015300
- Year Built
- 2003
- Length
- 20.4 m (66.9 ft)
- Max Span
- 18.6 m
- Width
- 8.2 m (26.9 ft)
- Lanes
- 2
- Daily Traffic
- 96
- Material
- Prestressed Concrete
- Design
- Box Beam or Girders - Multiple
- Owner
- City or Municipal Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $272,000
- Total Project Cost
- $314,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.