NH 25 over BEARCAMP RIVER

0.6 MI. TAMWORTH T.L. · County 003, New Hampshire · Built 2005 · 2 Lanes · 4,213 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good

Bridge Details

Structure #
020401140032800
Year Built
2005
Length
121 m (397 ft)
Max Span
24.4 m
Width
15.2 m (49.9 ft)
Lanes
2
Daily Traffic
4,213
Material
Steel Continuous
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$272,000
Total Project Cost
$314,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.