MEREDITH CENTER RD over OUTLET WICKWAS POND

1.3 MI NW LACONIA TL · County 001, New Hampshire · Built 2019 · 2 Lanes · 4,230 vehicles/day

Overall
Good
Deck
8
Very Good
Superstructure
8
Very Good
Substructure
7
Good

Condition Ratings

ComponentRatingDescription
Deck 8 Very Good
Superstructure 8 Very Good
Substructure 7 Good

Location

43.613758, -71.532467

This bridge is in worse condition than 27.7% of bridges in County 001. The average bridge in New Hampshire is 0 years old; this one is 7 years old.

Nearby Bridges

Bridge Details

Structure #
016701310010500
Year Built
2019
Length
19.2 m (63 ft)
Max Span
17.7 m
Width
10.4 m (34.1 ft)
Lanes
2
Daily Traffic
4,230
Material
Steel
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$272,000
Total Project Cost
$314,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.