I-89 NH 10 SB over NHRR(ABD)

2.1MI FROM ENFIELD T.L. · County 009, New Hampshire · Built 1966 · 2 Lanes · 16,677 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good

Bridge Details

Structure #
014401580011400
Year Built
1966
Reconstructed
2013
Length
44.8 m (147 ft)
Max Span
16.5 m
Width
12.8 m (42 ft)
Lanes
2
Daily Traffic
16,677
Material
Steel Continuous
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$272,000
Total Project Cost
$314,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.