GLENWOOD AVENUE over NH 16 SP TPK

.7 MI. FROM JCT. 16 · County 017, New Hampshire · Built 1957 · 2 Lanes · 2,660 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
8
Very Good
Substructure
7
Good

Bridge Details

Structure #
006501040014300
Year Built
1957
Reconstructed
2002
Length
73.2 m (240.2 ft)
Max Span
19.2 m
Width
12 m (39.4 ft)
Lanes
2
Daily Traffic
2,660
Material
Steel Continuous
Design
Stringer/Multi-beam or Girder
Owner
State Toll Authority
Last Inspected
N/A
Est. Improvement
$272,000
Total Project Cost
$314,000