IRR BIA RTE 40 over POPLAR RIVER

10 KM N OF PRYOR · County 085, Montana · Built 2000 · 2 Lanes · 200 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good

Condition Ratings

ComponentRatingDescription
Deck 7 Good
Superstructure 7 Good
Substructure 7 Good

Location

48.198542, -105.153

This bridge is in worse condition than 26.3% of bridges in County 085. The average bridge in Montana is 0 years old; this one is 26 years old.

Nearby Bridges

Bridge Details

Structure #
00000000000C620
Year Built
2000
Length
67.5 m (221.5 ft)
Max Span
33.8 m
Width
9.2 m (30.2 ft)
Lanes
2
Daily Traffic
200
Material
Prestressed Concrete
Design
Tee Beam
Owner
Bureau of Indian Affairs
Last Inspected
N/A
Est. Improvement
$0
Total Project Cost
$0
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.