US 7 SOUTH ST over RR HRR

@ ICE GLEN RD - HRR 69.66 · County 003, Massachusetts · Built 1909 · 2 Lanes · 12,420 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Poor
Deck
4
Poor
Superstructure
4
Poor
Substructure
6
Satisfactory

Bridge Details

Structure #
S260060E8DOT634
Year Built
1909
Reconstructed
1955
Length
33.5 m (109.9 ft)
Max Span
16.4 m
Width
16.2 m (53.1 ft)
Lanes
2
Daily Traffic
12,420
Material
Steel
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$6,030,000
Total Project Cost
$9,046,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.