I 495 RAMP D NB over WATER CANOE RIVER

I 495 NB RAMP TO 123 · County 005, Massachusetts · Built 1978 · 1 Lanes · 4,069 vehicles/day

Overall
Fair
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
6
Satisfactory

Bridge Details

Structure #
N230383RRDOTNBI
Year Built
1978
Length
14.6 m (47.9 ft)
Max Span
13.1 m
Width
7.7 m (25.3 ft)
Lanes
1
Daily Traffic
4,069
Material
Prestressed Concrete
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$281,000
Total Project Cost
$422,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.