NEW BOSTON ROAD over MILLER RIVER

16.09 KM N OF GARDNER · County 027, Massachusetts · Built 1900 · 2 Lanes · 50 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good

Bridge Details

Structure #
CEPNEDMA2510014
Year Built
1900
Reconstructed
1976
Length
12.6 m (41.3 ft)
Max Span
12.1 m
Width
6 m (19.7 ft)
Lanes
2
Daily Traffic
50
Material
Prestressed Concrete
Design
Slab
Owner
Corps of Engineers (Civil)
Last Inspected
N/A
Est. Improvement
$27,000
Total Project Cost
$30,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.