HWY FRONTAGE RD over OTHER RELIEF

AT SO BOSTON BYPASS RD. · County 025, Massachusetts · Built 1998 · 4 Lanes · 38,534 vehicles/day

Overall
Fair
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
6
Satisfactory

Bridge Details

Structure #
B16644929DOTNBI
Year Built
1998
Length
15.9 m (52.2 ft)
Max Span
14.8 m
Width
19.3 m (63.3 ft)
Lanes
4
Daily Traffic
38,534
Material
Prestressed Concrete
Design
Box Beam or Girders - Multiple
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$1,147,000
Total Project Cost
$1,721,000