I 93 RAMP SA-CN over I 93 RAMPS

NORTH BANK CHARLES RIVER · County 025, Massachusetts · Built 2004 · 2 Lanes · 20,359 vehicles/day

Overall
Fair
Deck
6
Satisfactory
Superstructure
7
Good
Substructure
7
Good

Bridge Details

Structure #
B166039PFDOTNBI
Year Built
2004
Length
128.7 m (422.2 ft)
Max Span
46.9 m
Width
10.9 m (35.8 ft)
Lanes
2
Daily Traffic
20,359
Material
Prestressed Concrete Continuous
Design
Segmental Box Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$2,814,000
Total Project Cost
$4,222,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.