DMPRC LTRAIL 3 over BONHAM CREEK

.25 MILES SE N2004 · County 053, Georgia · Built 2008 · 2 Lanes · 25 vehicles/day

Overall
Fair
Superstructure
6
Satisfactory
Substructure
5
Fair

Bridge Details

Structure #
DAPTRABEN0N2005
Year Built
2008
Length
7.7 m (25.3 ft)
Max Span
7.7 m
Width
29.3 m (96.1 ft)
Lanes
2
Daily Traffic
25
Material
Steel
Design
Arch - Deck
Owner
Other
Last Inspected
N/A
Est. Improvement
$1,000
Total Project Cost
$2,000