BUENA VISTA ROAD over UPATOI CREEK
.1 KM W/O HOURGLASS RD · County 215, Georgia · Built 1990 · 2 Lanes · 100 vehicles/day
Overall
Deck
8
Very Good
Superstructure
8
Very Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 8 | Very Good |
| Superstructure | 8 | Very Good |
| Substructure | 7 | Good |
Location
32.445181, -84.756561
This bridge is in worse condition than 41.5% of bridges in County 215. The average bridge in Georgia is 0 years old; this one is 36 years old.
Nearby Bridges
HOURGLASS ROAD over PINE KNOT CREEK
Built 2010
RESACA ROAD over SALLY BRANCH
Built 2017
DMPRC LTRAIL 3 over SALLY BRANCH
Built 2008
BUENA VISTA ROAD over PINE KNOT CREEK
Built 1977
DMPRC LTRAIL 4 over SALLY BRANCH
Built 2007
DMPRC LTRAIL 1 over BONHAM CREEK
Built 2008
DMPRC LTRAIL 3 over BONHAM CREEK
Built 2008
CARMOUCHE RANGE RD over UPATOI CREEK
Built 2007
DMPRC LTRAIL 4 over BONHAM CREEK
Built 2008
DMPRC LTRAIL 5A over BONHAM CREEK
Built 2008
Bridge Details
- Structure #
- 0000000000M9355
- Year Built
- 1990
- Length
- 85.6 m (280.8 ft)
- Max Span
- 17.8 m
- Width
- 14.4 m (47.2 ft)
- Lanes
- 2
- Daily Traffic
- 100
- Material
- Prestressed Concrete
- Design
- Stringer/Multi-beam or Girder
- Owner
- Other
- Last Inspected
- N/A
- Est. Improvement
- $1,000
- Total Project Cost
- $2,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.