SR 247 CONN. over I-75 (EXIT 146) @ 146.12

3.1 MI SSE OF BYRON · County 225, Georgia · Built 1962 · 5 Lanes · 23,600 vehicles/day

Overall
Fair
Deck
6
Satisfactory
Superstructure
7
Good
Substructure
7
Good

Bridge Details

Structure #
000000022500100
Year Built
1962
Reconstructed
1986
Length
75.3 m (247 ft)
Max Span
25.6 m
Width
25.8 m (84.6 ft)
Lanes
5
Daily Traffic
23,600
Material
Steel Continuous
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$1,755,000
Total Project Cost
$2,632,000