WILLOW SPRINGS ROA over SILVER COMET TRAIL
4 MI W OF DALLAS · County 223, Georgia · Built 2014 · 2 Lanes · 320 vehicles/day
Overall
Deck
7
Good
Superstructure
8
Very Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 7 | Good |
| Superstructure | 8 | Very Good |
| Substructure | 7 | Good |
Location
33.9341, -84.910897
This bridge is in worse condition than 45.2% of bridges in County 223. The average bridge in Georgia is 0 years old; this one is 12 years old.
Nearby Bridges
US 278 (WBL) over PUMPKINVINE CREEK
Built 1930
US 278 (EBL) over PUMPKINVINE CREEK
Built 1992
MOUNT OLIVET ROAD over PUMPKINVINE CREEK
Built 1969
STATE ROUTE 120 over LANE CREEK
Built 2002
HULSEY TOWN ROAD over BLUFFY CREEK
Built 1985
STATE ROUTE 6 BUSI over WEAVER CREEK
Built 1940
STATE ROUTE 61 over PUMPKINVINE CREEK
Built 1993
S MAIN ST over WEAVER CREEK
Built 2016
SEABOARD DRIVE over GRIFFIN CREEK
Built 2011
HIGH SHOALS ROAD over RACCOON CREEK
Built 2019
Bridge Details
- Structure #
- 000000022351000
- Year Built
- 2014
- Length
- 34.1 m (111.9 ft)
- Max Span
- 34.1 m
- Width
- 13.3 m (43.6 ft)
- Lanes
- 2
- Daily Traffic
- 320
- Material
- Concrete
- Design
- Stringer/Multi-beam or Girder
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $9,945,000
- Total Project Cost
- $14,918,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.