SPALDING DRIVE over CROOKED CREEK

6.6 MI SE OF ROSWELL · County 121, Georgia · Built 2022 · 2 Lanes · 20,700 vehicles/day

Overall
Good
Deck
8
Very Good
Superstructure
8
Very Good
Substructure
8
Very Good

Bridge Details

Structure #
000000012154230
Year Built
2022
Length
48.8 m (160.1 ft)
Max Span
24.4 m
Width
23.5 m (77.1 ft)
Lanes
2
Daily Traffic
20,700
Material
Concrete
Design
Stringer/Multi-beam or Girder
Owner
City or Municipal Highway Agency
Last Inspected
N/A
Est. Improvement
$14,208,000
Total Project Cost
$21,312,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.