CAPITOL AVE. over I-20- I-75 RMP- I-20 RMP

I-20 & I-75 INTERCHANGE · County 121, Georgia · Built 1988 · 6 Lanes · 12,300 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good

Bridge Details

Structure #
000000012106530
Year Built
1988
Length
165.2 m (542 ft)
Max Span
59.7 m
Width
26.9 m (88.3 ft)
Lanes
6
Daily Traffic
12,300
Material
Prestressed Concrete Continuous
Design
Box Beam or Girders - Multiple
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$4,428,000
Total Project Cost
$6,642,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.