PRIEST ROAD over I-75

7.2 MI W OF WOODSTOCK · County 057, Georgia · Built 1976 · 2 Lanes · 3,270 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good

Bridge Details

Structure #
000000005700620
Year Built
1976
Length
127.1 m (417 ft)
Max Span
39.9 m
Width
14.1 m (46.3 ft)
Lanes
2
Daily Traffic
3,270
Material
Steel Continuous
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$1,629,000
Total Project Cost
$2,444,000