JIMMY DELOACH PKWY over NORFOLK SOUTHERN RAILROA
PORT WENTWORTH CITY LIMIT · County 051, Georgia · Built 2015 · 4 Lanes · 15,000 vehicles/day
Overall
Deck
8
Very Good
Superstructure
8
Very Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 8 | Very Good |
| Superstructure | 8 | Very Good |
| Substructure | 7 | Good |
Location
32.153867, -81.176186
This bridge is in worse condition than 18.3% of bridges in County 051. The average bridge in Georgia is 0 years old; this one is 11 years old.
Nearby Bridges
JIMMY DELOACH PKWY over SR-30 (BONNY BRIDGE ROAD
Built 2015
JIMMY DELOACH PKWY over ST. AUGUSTINE CREEK TRIB
Built 2015
JIMMY DELOACH PARK over CROSSGATE ROAD
Built 2015
JIMMY DELOACH PKWY over SONNY DIXON INTERCHANGE
Built 2015
OCEAN HIGHWAY over NORFOLK SOUTHERN RAILROA
Built 2011
JIMMY DELOACH PKY over SR 21 NORFORK SOUTHERN
Built 2001
JIMMY DELOACH PKWY over GRANGE ROAD
Built 2015
HOULIHAN BRIDGE over SAVANNAH RIVER
Built 2024
SR 21 NBL over SAINT AUGUSTINE CREEK
Built 1980
SR 21 SBL over SAINT AUGUSTINE CREEK
Built 1980
Bridge Details
- Structure #
- 000000005151010
- Year Built
- 2015
- Length
- 36.6 m (120.1 ft)
- Max Span
- 36.6 m
- Width
- 24.4 m (80.1 ft)
- Lanes
- 4
- Daily Traffic
- 15,000
- Material
- Prestressed Concrete
- Design
- Stringer/Multi-beam or Girder
- Owner
- State Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $10,656,000
- Total Project Cost
- $15,984,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.