LEVEL 4 SE TERMINA over 84TH AVENUE
SE CORNER TERM BLDG · County 031, Colorado · Built 2014 · 2 Lanes · 8,856 vehicles/day
Overall
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 7 | Good |
| Superstructure | 7 | Good |
| Substructure | 7 | Good |
Location
39.847775, -104.672497
This bridge is in worse condition than 26.5% of bridges in County 031. The average bridge in Colorado is 0 years old; this one is 12 years old.
Nearby Bridges
SE 4/5TH LEVEL PAR over 84TH AVENUE
Built 2017
LEVEL 5 SE TERMINA over 84TH AVENUE
Built 2014
LEVEL 6 SE TERMINA over 84TH AVENUE
Built 2014
E 2ND LEVEL PARKIN over PARKING LOT
Built 1993
SE 2ND LEVEL over PARKING LOT
Built 2017
SE 2ND LEVEL PARKI over PARKING GARAGE
Built 1993
LEVEL 6 SW TERMINA over 84TH AVENUE
Built 2014
LEVEL 5 SW TERMINA over 84TH AVENUE
Built 2014
LEVEL 4 SW TERMINA over 84TH AVENUE
Built 2014
SW 4/5TH LEVEL PAR over 84TH AVENUE
Built 2007
Bridge Details
- Structure #
- D-31-PB-723A
- Year Built
- 2014
- Length
- 133.7 m (438.6 ft)
- Max Span
- 35.2 m
- Width
- 12 m (39.4 ft)
- Lanes
- 2
- Daily Traffic
- 8,856
- Material
- Prestressed Concrete Continuous
- Design
- Stringer/Multi-beam or Girder
- Owner
- Other Local Agencies
- Last Inspected
- N/A
- Est. Improvement
- $0
- Total Project Cost
- N/A
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.