Helmet Peak over Large Wash
5.5 mi West of I 19 · County 019, Arizona · Built 1977 · 2 Lanes · 1,956 vehicles/day
Overall
Culvert
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Culvert | 7 | Good |
Location
31.9572, -111.071119
This bridge is in worse condition than 69.1% of bridges in County 019. The average bridge in Arizona is 0 years old; this one is 49 years old.
Nearby Bridges
Mission Rd over Medium Wash
Built 1996
Helmet Peak over Large Wash
Built 1977
I 19; NB & SB over Wash
Built 1978
Helmet Peak Road over Large Wash
Built 1977
IRR Mission Rd over Mine Haul Road
Built 1973
I 19; Ramp A SB over Wash
Built 1969
I 19; SB over Wash
Built 1969
I 19; NB & SB over Wash
Built 1969
I 19; NB & SB over Wash
Built 1969
Helmet Peak Rd over I 19
Built 1969
Bridge Details
- Structure #
- 08634
- Year Built
- 1977
- Length
- 13.1 m (43 ft)
- Max Span
- 3 m
- Width
- 23 m (75.5 ft)
- Lanes
- 2
- Daily Traffic
- 1,956
- Material
- Concrete Continuous
- Design
- Culvert
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $0
- Total Project Cost
- $0
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.