Helmet Peak Rd over I 19

3.6 mi N of Jct B 19 · County 019, Arizona · Built 1969 · 2 Lanes · 36,001 vehicles/day

Overall
Fair
Deck
8
Very Good
Superstructure
6
Satisfactory
Substructure
7
Good

Condition Ratings

ComponentRatingDescription
Deck 8 Very Good
Superstructure 6 Satisfactory
Substructure 7 Good

Location

31.9579, -110.9881

This bridge is in worse condition than 80.8% of bridges in County 019. The average bridge in Arizona is 0 years old; this one is 57 years old.

Nearby Bridges

Bridge Details

Structure #
01356
Year Built
1969
Length
76.8 m (252 ft)
Max Span
25 m
Width
17.6 m (57.7 ft)
Lanes
2
Daily Traffic
36,001
Material
Concrete Continuous
Design
Box Beam or Girders - Single or Spread
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$0
Total Project Cost
$0