PINE ST-BOREN AVE over I-5

1.6 N JCT I-90 · County 033, Washington · Built 1965 · 3 Lanes · 24,000 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good

Condition Ratings

ComponentRatingDescription
Deck 7 Good
Superstructure 7 Good
Substructure 7 Good

Location

47.614622, -122.329558

This bridge is in worse condition than 12.8% of bridges in County 033. The average bridge in Washington is 0 years old; this one is 61 years old.

Nearby Bridges

Bridge Details

Structure #
0007409D0000000
Year Built
1965
Length
251.5 m (825.1 ft)
Max Span
37.2 m
Width
18.6 m (61 ft)
Lanes
3
Daily Traffic
24,000
Material
Concrete Continuous
Design
Box Beam or Girders - Multiple
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$10,384,000
Total Project Cost
$20,769,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.