SBL CHAMBERLAYNE over RTE I 95
0.44 TO I-95 & 0.71 NCL R · County 087, Virginia · Built 1962 · 2 Lanes · 5,609 vehicles/day
Structurally Deficient
— One or more key components rated 4 (Poor) or below
Overall
Deck
4
Poor
Superstructure
5
Fair
Substructure
4
Poor
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 4 | Poor |
| Superstructure | 5 | Fair |
| Substructure | 4 | Poor |
Location
37.611825, -77.446939
This bridge is in worse condition than 97% of bridges in County 087. The average bridge in Virginia is 0 years old; this one is 64 years old.
Nearby Bridges
ACCESS ROAD over UPHAM BROOK
Built 1962
SBL CHAMBERLAYNE over RTE I 95 & UPHAM BROOK
Built 1962
SBL ROUTE 0095 over UPHAM BROOK
Built 1962
NBL CHAMBERLAYNE over UPHAM BROOK
Built 1962
NBL ROUTE 0095 over UPHAM BROOK
Built 1962
BROOK ROAD over ROUTE I-95
Built 1958
BELLEVUE AVENUE over ROUTE I-95
Built 1958
ROUTE 0095 over FLIPPEN CREEK
Built 1962
HILLIARD ROAD over NORTH RUN
Built 1947
DUMBARTON ROAD over ROUTE I-95
Built 1958
Bridge Details
- Structure #
- 000000000010008
- Year Built
- 1962
- Reconstructed
- 1992
- Length
- 115.1 m (377.6 ft)
- Max Span
- 36 m
- Width
- 9.4 m (30.8 ft)
- Lanes
- 2
- Daily Traffic
- 5,609
- Material
- Steel
- Design
- Stringer/Multi-beam or Girder
- Owner
- State Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $200,000,000
- Total Project Cost
- $300,000,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.