KATY HOCKLEY CUTFF over S MAYDE CR
0.95 MI S OF FM 529 · County 201, Texas · Built 1989 · 2 Lanes · 3,708 vehicles/day
Overall
Deck
6
Satisfactory
Superstructure
8
Very Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 6 | Satisfactory |
| Superstructure | 8 | Very Good |
| Substructure | 7 | Good |
Location
29.861072, -95.807033
This bridge is in worse condition than 54.5% of bridges in County 201. The average bridge in Texas is 0 years old; this one is 37 years old.
Nearby Bridges
FM 529 over SOUTH MAYDE CREEK
Built 1968
KATY HOCKLEY RD over DRAINAGE DITCH
Built 1960
Elyson Falls Dr over Detention Basin
Built 2018
FM 529(Freeman Rd) over Drainage Ditch
Built 2019
PEEK RD over S MAYDE CR
Built 1990
LONGENBAUGH RD over BEAR CREEK
Built 2011
KATY HOCKLEY RD over DRAINAGE DITCH
Built 1960
KATY HOCKLEY CUTOF over BEAR CREEK
Built 1993
FM 529 over BEAR CREEK
Built 1968
Winward Lake Dr over Drainage Ditch
Built 2021
Bridge Details
- Structure #
- 121020AA0201001
- Year Built
- 1989
- Length
- 18.9 m (62 ft)
- Max Span
- 18.3 m
- Width
- 11 m (36.1 ft)
- Lanes
- 2
- Daily Traffic
- 3,708
- Material
- Prestressed Concrete
- Design
- Box Beam or Girders - Multiple
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $0
- Total Project Cost
- $0
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.