FAP 30 over RICHLAND CREEK

.4 MILE WEST OF DAYTON · County 143, Tennessee · Built 1956 · 2 Lanes · 6,443 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Poor
Deck
4
Poor
Superstructure
4
Poor
Substructure
5
Fair

Bridge Details

Structure #
72SR0300005
Year Built
1956
Length
82.8 m (271.7 ft)
Max Span
13.1 m
Width
10.5 m (34.4 ft)
Lanes
2
Daily Traffic
6,443
Material
Concrete
Design
Tee Beam
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$666,000
Total Project Cost
$1,000,000