TIDEWATER DR over BUCKEYE BROOK
0.2 MI S OF RI 117 · County 003, Rhode Island · Built 1935 · 2 Lanes · 3,277 vehicles/day
Overall
Deck
8
Very Good
Superstructure
8
Very Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 8 | Very Good |
| Superstructure | 8 | Very Good |
| Substructure | 7 | Good |
Location
41.712117, -71.375267
This bridge is in worse condition than 14.8% of bridges in County 003. The average bridge in Rhode Island is 0 years old; this one is 91 years old.
Nearby Bridges
LAKE SHORE DRIVE over BUCKEYE BROOK
Built 2016
AIRPORT ELEV RDWY over ARRIVAL ROAD
Built 1996
AIRPORT ELEV RDWY over PLAZA TERMINALS PARKING
Built 1996
AIRPORT ELEV RDWY over PLAZA TERMINALS PARKING
Built 1996
CRESCENT VIEW AV over BULLOCK COVE
Built 2007
AIRPORT CONNECTOR over US 1 POST RD
Built 1968
RI 37 EB & WB over US 1 POST RD
Built 1965
AIRPORT CONNECTOR over AMTRAK
Built 1967
CORONADO RD over AMTRAK
Built 1980
AIRPORT CONNECTOR over JEFFERSON BLVD
Built 1967
Bridge Details
- Structure #
- 000000000011410
- Year Built
- 1935
- Length
- 13.4 m (44 ft)
- Max Span
- 12.5 m
- Width
- 13.4 m (44 ft)
- Lanes
- 2
- Daily Traffic
- 3,277
- Material
- Prestressed Concrete
- Design
- Box Beam or Girders - Single or Spread
- Owner
- City or Municipal Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $279,000
- Total Project Cost
- $725,000