PR 867 4.5 KM over CHANNEL
4.6 KM EAST OF TOA BAJA · County 137, Puerto Rico · Built 1980 · 2 Lanes · 19,200 vehicles/day
Structurally Deficient
— One or more key components rated 4 (Poor) or below
Overall
Deck
5
Fair
Superstructure
5
Fair
Substructure
1
Imminent Failure
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 5 | Fair |
| Superstructure | 5 | Fair |
| Substructure | 1 | Imminent Failure |
Location
18.440206, -66.221306
This bridge is in worse condition than 96.4% of bridges in County 137. The average bridge in Puerto Rico is 0 years old; this one is 46 years old.
Nearby Bridges
PR 867 over CHANNEL
Built 1980
PR-867 KM 0.8 over UNNAMED CREEK
Built 2003
PR 22 over LOCAL ROAD
Built 1981
PR 22 over PR 865
Built 1981
METRO URBANO ROAD over PR 22
Built 2013
PR 165 KM 18.15 over COCAL RIVER
Built 1958
PR 22 over CREEK
Built 1981
CONCHA CAMARON ST. over CHANNEL
Built 1973
CORUJO COLLECTOR over HONDO RIVER
Built 1967
PR 165 25.5 KM over COCAL RIVER
Built 1959
Bridge Details
- Structure #
- 017601
- Year Built
- 1980
- Length
- 9.1 m (29.9 ft)
- Max Span
- 7.9 m
- Width
- 10.7 m (35.1 ft)
- Lanes
- 2
- Daily Traffic
- 19,200
- Material
- Concrete
- Design
- Slab
- Owner
- State Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $190,000
- Total Project Cost
- $284,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.