OR 38 (HWY 045) over PARADISE CREEK

076 MI W ELKTON · County 019, Oregon · Built 1932 · 2 Lanes · 3,554 vehicles/day

Overall
Fair
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
8
Very Good

Bridge Details

Structure #
01697 045 02828
Year Built
1932
Reconstructed
1998
Length
60.8 m (199.5 ft)
Max Span
20.4 m
Width
14 m (45.9 ft)
Lanes
2
Daily Traffic
3,554
Material
Concrete Continuous
Design
Tee Beam
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$644,000
Total Project Cost
$1,030,000