I-89 SB over TURKEY POND

1.5 MI NW JCT RT 13 · County 013, New Hampshire · Built 1959 · 3 Lanes · 20,703 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Poor
Deck
7
Good
Superstructure
7
Good
Substructure
4
Poor

Bridge Details

Structure #
005201650002900
Year Built
1959
Reconstructed
1992
Length
73.2 m (240.2 ft)
Max Span
25.3 m
Width
17.4 m (57.1 ft)
Lanes
3
Daily Traffic
20,703
Material
Steel
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$272,000
Total Project Cost
$314,000