NH 16 SB over DEAD RIVER

1.5 MI N OF GORHAM TL · County 007, New Hampshire · Built 1931 · 2 Lanes · 4,241 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
8
Very Good
Substructure
7
Good

Bridge Details

Structure #
002302350006100
Year Built
1931
Reconstructed
1995
Length
7.3 m (24 ft)
Max Span
6.7 m
Width
15.7 m (51.5 ft)
Lanes
2
Daily Traffic
4,241
Material
Prestressed Concrete
Design
Box Beam or Girders - Multiple
Owner
City or Municipal Highway Agency
Last Inspected
N/A
Est. Improvement
$272,000
Total Project Cost
$314,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.