RMP TROP WB TO 15N over I 15N OFF RAMP TO FRANK

LAS VEGAS · County 003, Nevada · Built 2002 · 2 Lanes · 31,000 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
8
Very Good
Substructure
8
Very Good

Bridge Details

Structure #
I2356
Year Built
2002
Length
37 m (121.4 ft)
Max Span
36.5 m
Width
15.7 m (51.5 ft)
Lanes
2
Daily Traffic
31,000
Material
Prestressed Concrete
Design
Box Beam or Girders - Multiple
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$1,000,000
Total Project Cost
$1,000,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.