COUNTY ROAD 130 over USBR MAIN CANAL 066
6M SW FAIRVIEW · County 083, Montana · Built 2009 · 2 Lanes · 100 vehicles/day
Overall
Deck
6
Satisfactory
Superstructure
7
Good
Substructure
6
Satisfactory
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 6 | Satisfactory |
| Superstructure | 7 | Good |
| Substructure | 6 | Satisfactory |
Location
47.790833, -104.108639
This bridge is in worse condition than 36.1% of bridges in County 083. The average bridge in Montana is 0 years old; this one is 17 years old.
Nearby Bridges
COUNTY ROAD 129 over USBR MAIN CANAL 067
Built 2015
COUNTY ROAD 131 over USBR MAIN CANAL 072
Built 2000
S 200 over FIRST HAY CREEK
Built 1986
COUNTY ROAD 131 over USBR MAIN CANAL 080
Built 1998
COUNTY ROAD 130 over FIRST HAY CREEK 098
Built 2009
S 200 over SECOND HAY CREEK
Built 1986
COUNTY ROAD 211 over SECOND HAY CREEK 065
Built 2018
COUNTY ROAD 128 over USBR MAIN CANAL 089
Built 1997
COUNTY ROAD 132 over USBR MAIN CANAL 064
Built 1985
COUNTY ROAD 202 over FIRST HAY CREEK 024
Built 1997
Bridge Details
- Structure #
- L42239000+01001
- Year Built
- 2009
- Length
- 18.3 m (60 ft)
- Max Span
- 18.3 m
- Width
- 9.5 m (31.2 ft)
- Lanes
- 2
- Daily Traffic
- 100
- Material
- Prestressed Concrete
- Design
- Tee Beam
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $38,000
- Total Project Cost
- $57,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.