RICKETT ROAD over HURON RIVER

SEC 17-18 GREEN OAK TWP · County 093, Michigan · Built 1973 · 2 Lanes · 5,910 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Poor
Deck
4
Poor
Superstructure
4
Poor
Substructure
8
Very Good

Bridge Details

Structure #
000000000005862
Year Built
1973
Reconstructed
2001
Length
22.5 m (73.8 ft)
Max Span
21.9 m
Width
11.5 m (37.7 ft)
Lanes
2
Daily Traffic
5,910
Material
Prestressed Concrete
Design
Tee Beam
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
N/A
Total Project Cost
N/A
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.