ST 28 MAIN ST over WATER PARKERS RIVER

2 MI W OF DENNIS TL · County 001, Massachusetts · Built 2021 · 2 Lanes · 23,275 vehicles/day

Overall
Good
Deck
8
Very Good
Superstructure
8
Very Good
Substructure
8
Very Good

Bridge Details

Structure #
Y01002BNFDOTNBI
Year Built
2021
Length
11.6 m (38.1 ft)
Max Span
9.2 m
Width
17.4 m (57.1 ft)
Lanes
2
Daily Traffic
23,275
Material
Prestressed Concrete
Design
Slab
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$0
Total Project Cost
$0
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.