HWY PLM ISLN TPK over WATER PLUM ISLAND RIVER

0.4 MI W OF SUNSET DR · County 009, Massachusetts · Built 1973 · 2 Lanes · 9,172 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Serious
Deck
6
Satisfactory
Superstructure
3
Serious
Substructure
6
Satisfactory

Bridge Details

Structure #
N100112Y6DOTNBI
Year Built
1973
Length
41.1 m (134.8 ft)
Max Span
29 m
Width
11.7 m (38.4 ft)
Lanes
2
Daily Traffic
9,172
Material
Steel
Design
Movable - Bascule
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$6,755,000
Total Project Cost
$10,133,000