I 495 over ST 28 WAREHAM ST

3 M W OF CARVER TL · County 023, Massachusetts · Built 1958 · 6 Lanes · 41,355 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good

Bridge Details

Structure #
M18049460DOTNBI
Year Built
1958
Reconstructed
1988
Length
58.8 m (192.9 ft)
Max Span
24.4 m
Width
40.1 m (131.6 ft)
Lanes
6
Daily Traffic
41,355
Material
Steel Continuous
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$1,536,000
Total Project Cost
$2,305,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.