HWY SHIRLEY RD over ST 2

EXIT 105 / MM 104.9 · County 027, Massachusetts · Built 1951 · 2 Lanes · 4,860 vehicles/day

Overall
Fair
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
7
Good

Bridge Details

Structure #
L0201620GDOTNBI
Year Built
1951
Reconstructed
1993
Length
46 m (150.9 ft)
Max Span
22.6 m
Width
11.7 m (38.4 ft)
Lanes
2
Daily Traffic
4,860
Material
Steel Continuous
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$3,570,000
Total Project Cost
$5,356,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.