I 90 WB over COMB CNTRL MLBRY & PWRR

.9 MI E OF I-290 · County 027, Massachusetts · Built 1957 · 3 Lanes · 11,216 vehicles/day

Overall
Fair
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
6
Satisfactory

Bridge Details

Structure #
A170424KGDOTNBI
Year Built
1957
Reconstructed
1980
Length
121.6 m (399 ft)
Max Span
32 m
Width
17.2 m (56.4 ft)
Lanes
3
Daily Traffic
11,216
Material
Steel Continuous
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$4,468,000
Total Project Cost
$6,703,000