TR 282A over OAK BRANCH
2.7 N ASSUMPTION · County 021, Illinois · Built 1966 · 2 Lanes · 150 vehicles/day
Overall
Deck
7
Good
Superstructure
6
Satisfactory
Substructure
5
Fair
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 7 | Good |
| Superstructure | 6 | Satisfactory |
| Substructure | 5 | Fair |
Location
39.562003, -89.081083
This bridge is in worse condition than 49.4% of bridges in County 021. The average bridge in Illinois is 0 years old; this one is 60 years old.
Nearby Bridges
TR 169 over OAK BRANCH
Built 1919
TR 185 over OAK BRANCH
Built 1900
TR 282A over OAK BRANCH
Built 1966
TR 169 over BID GEORGE BR
Built 2009
CH 9 FAS 1647 over OAK BRANCH
Built 1977
TR 185 over BIG GEORGE BRANCH
Built 1962
TR 151A over Big George Branch
Built 2015
TR 193 over BIG GEORGE BRANCH
Built 1963
CH-6 FAS 642 over OAK BRANCH
Built 1988
TR 272 A over OAK BRANCH
Built 1949
Bridge Details
- Structure #
- 011322500000000
- Year Built
- 1966
- Length
- 9.8 m (32.2 ft)
- Max Span
- 9.1 m
- Width
- 8.4 m (27.6 ft)
- Lanes
- 2
- Daily Traffic
- 150
- Material
- Steel
- Design
- Stringer/Multi-beam or Girder
- Owner
- Town or Township Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $78,000
- Total Project Cost
- $117,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.