SQUAW CREEK RD over SQUAW CREEK
2.9 N. 3.8 W. CLAYTON · County 037, Idaho · Built 1960 · 2 Lanes · 300 vehicles/day
Structurally Deficient
— One or more key components rated 4 (Poor) or below
Overall
Deck
4
Poor
Superstructure
4
Poor
Substructure
5
Fair
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 4 | Poor |
| Superstructure | 4 | Poor |
| Substructure | 5 | Fair |
Location
44.315506, -114.474558
This bridge is in worse condition than 88.9% of bridges in County 037. The average bridge in Idaho is 0 years old; this one is 66 years old.
Nearby Bridges
SQUAW CREEK RD over SQUAW CREEK
Built 1960
SQUAW CREEK ROAD over SQUAW CREEK
Built 1960
SQ___ CREEK ROAD over PAASASIKWANA NAOKWAIDE
Built 1964
SQ___ CREEK ROAD over PAASASIKWANA NAOKWAIDE
Built 1964
THOMPSON CR ROAD over THOMPSON CREEK
Built 1982
TREALOR CREEK ROAD over SQ___ CREEK
Built 1966
SQUAW CREEK RD over SQUAW CREEK
Built 1960
SH 75 over SALMON RIVER; W. CLAYTON
Built 2008
SQUAW CREEK RD over SALMON RIVER;SW.CLAYTON
Built 1970
SH 75 over SALMON RIVER;SLATE CR BR
Built 2011
Bridge Details
- Structure #
- 000000000031755
- Year Built
- 1960
- Reconstructed
- 1984
- Length
- 7.6 m (24.9 ft)
- Max Span
- 7 m
- Width
- 8.5 m (27.9 ft)
- Lanes
- 2
- Daily Traffic
- 300
- Material
- Prestressed Concrete
- Design
- Tee Beam
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $223,000
- Total Project Cost
- $334,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.