RUBY CREEK RD over RUBY CREEK(#4)

3.3 N. 0.8 W. NAPLES · County 021, Idaho · Built 1970 · 1 Lanes · 30 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Poor
Deck
8
Very Good
Superstructure
6
Satisfactory
Substructure
4
Poor

Bridge Details

Structure #
000000000030345
Year Built
1970
Reconstructed
1999
Length
7.3 m (24 ft)
Max Span
7 m
Width
4.9 m (16.1 ft)
Lanes
1
Daily Traffic
30
Material
Steel
Design
Stringer/Multi-beam or Girder
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
$208,000
Total Project Cost
$312,000