SQUAW VALLEY over UPPER W.BRANCH PRIEST R.
1.9 S. 5.6 W. COOLIN · County 017, Idaho · Built 1975 · 2 Lanes · 40 vehicles/day
Overall
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
5
Fair
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 6 | Satisfactory |
| Superstructure | 6 | Satisfactory |
| Substructure | 5 | Fair |
Location
48.455394, -116.970956
This bridge is in worse condition than 66.3% of bridges in County 017. The average bridge in Idaho is 0 years old; this one is 51 years old.
Nearby Bridges
FS ROUTE NO. 2694 over GOOSE CREEK
Built 1990
FS ROUTE NO. 312 over UPPER W. BRANCH
Built 1954
SH 57 over UPPER W.BRANCH PRIEST R.
Built 1937
FS ROUTE NO. 2730 over CONSULAS CREEK
Built 2010
NO DATA ENTERED over UPPER WEST BRANCH
Built 1989
S5779;DICKENSHEET over PRIEST RIVER
Built 1951
FS ROUTE NO. 659 over UPPER W. BRANCH
Built 1954
FS ROUTE NO. 1075 over UPPER W. BRANCH
Built 1979
FS ROUTE NO. 312 over UPPER W. BRANCH
Built 1954
FS ROUTE N0. 1312 over MOORES CREEK
Built 1980
Bridge Details
- Structure #
- 000000000030170
- Year Built
- 1975
- Length
- 11.6 m (38.1 ft)
- Max Span
- 11.3 m
- Width
- 9.8 m (32.2 ft)
- Lanes
- 2
- Daily Traffic
- 40
- Material
- Concrete
- Design
- Tee Beam
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $317,000
- Total Project Cost
- $475,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.