ACCESS ROAD over PARADISE CREEK
AT MOSCOW WCL · County 057, Idaho · Built 1953 · 1 Lanes · 20 vehicles/day
Overall
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
6
Satisfactory
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 6 | Satisfactory |
| Superstructure | 6 | Satisfactory |
| Substructure | 6 | Satisfactory |
Location
46.732181, -117.024583
This bridge is in worse condition than 46.2% of bridges in County 057. The average bridge in Idaho is 0 years old; this one is 73 years old.
Nearby Bridges
STADIUM DR over PARADISE CREEK
Built 2010
STC 7704;PERIMETER over PARADISE CREEK
Built 1953
STADIUM DR over PARADISE CREEK
Built 2010
PARADISE CRK ST over PARADISE CREEK
Built 1967
STC 7834;LINE ST over PARADISE CREEK
Built 2010
STC 7664;W. 6TH ST over PARADISE CREEK
Built 1916
COLLEGE STREET over PARADISE CREEK
Built 1915
US 95 over PARADISE CREEK
Built 2000
SAND ROAD over S.FK.PALOUSE RIVER
Built 1955
STC7684;SAND ROAD over S.FK.PALOUSE RIVER
Built 1971
Bridge Details
- Structure #
- 000000000029755
- Year Built
- 1953
- Length
- 9.8 m (32.2 ft)
- Max Span
- 9.4 m
- Width
- 6.2 m (20.3 ft)
- Lanes
- 1
- Daily Traffic
- 20
- Material
- Concrete
- Design
- Tee Beam
- Owner
- City or Municipal Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $249,000
- Total Project Cost
- $374,000